Consider the following statements :The critical path in a network plan of aproject1.
helps in planning efficient timeschedule2.
indicates the shortest path intime3.
helps in crashing the projectjudiciously4.
helps in encouraging discipline inexecution.
Of these statements
1, 3 and 4 are correct
 
1, 2, 3 and 4 are correct
 
1 and 4 are correct
 
2 and 3 are correct
 