Duration along the critical path defines which of the following ?1. Shortest durationneeded2.
Shortest durationpermissible3.
Longest durationneeded4.
Longest duration permissibleSelect the correct answer using the code given below

1 and 2 only
 
1 and 4 only
 
2 and 3 only
 
3 and 4 only
 