Consider the following statements :A critical activity in a CPM networkhas1.
The longest duration of allactivities2.
zero totalfloat3.
zero forfloat4.
The shortest duration of all activitieswhich one of the statements given above are correct

1 and 2
 
1 and 3
 
2 and 3
 
3 and 4
 

Answer