A team of 200 wagers undertakes building work of a bridge. The total time allocated to build the entire bridge is 20 days. After 10 days since start, 200 more wagers join the team and together the team completes the bridge in required time. If the original team do not get those 200 extra wagers, how many days they would be behind schedule to complete building the bridge

Comments and Answers (2)

Lalit

Lalit

What is the correct solution?

Richa

Richa

does anyone know the correct answer