A and B can separately do a piece of work in 20 and 15 days respectively. they worked to together for 6 days, after whch B was replaced by C. If the work was finished in next 4 days, then the number of days in which C alone could do the work will be

🗓 Dec 14, 2021

Answer is "40"

Comments and Discussions

You don't need to login to post your comment

Comments:
30
Views:
60k
Likes:
120k
votes
Mia 🌐 India
Thanks for the answer
Was this answer helpful?
votes
Alexandra 🌐 India
Students helping students, nice idea
Was this answer helpful?

Was your question answered?

Thanks for the feedback! ✅

Want to get famous? 📸

Answer question and get 🤩 high-lighted on our homepage.

Just Automated Logo

© 2017-2022 Foxoyo™
All rights reserved.

Facebook Connect with us