A and B together can do a piece of work in 12 days, which B and C together can do in 16 days. After A has been working at it for 5 days and B for 7 days, C finishes in 13 days. In how many days C alone will do the work

Comments and Answers (2)

please anyone explain this answer

Shumbham

Shumbham

please explain answer

Avatar