In drawing AOA networks and making time computations, the following processes are involved :1. Activity listing2. Work breakdown structure3. Activity time allotment4. Consideration of available resources for each activity5. Activity dependencies6. Float computations7. Backward path computation8. Project duration9. Forward path computationWhat is the correct sequence of the processes given above