Tek bahadur shrestha ~ Kathmandu
🌐 India
Sravan can do a work in 1 day is( 1/25 -1/75)=2/75
sravan worked 8 days so, he completed 8*2/75parts of whole work.
so his share is 16*225/75=48
sravan worked 8 days so, he completed 8*2/75parts of whole work.
so his share is 16*225/75=48
Was this answer helpful?
Anonymous
🌐 India
A pipe in 1 minute can fill 1/20 th of the tank. Similarly B pipe can fill 1/30 th of the tank per minute. When both pipes are used to gether for a minute then the amont of 1/20+1/30=5/60of the work. This amounts to 1/12 of the work. Complete tank will take 12 minutes Ans
Was this answer helpful?
Anonymous
🌐 India
Two pipes A and B can fill a tank in 20 and 30 minutes respectively. If both the pipes are used together, then how long will it take to fill the tank?